A Typical Log Home Construction Schedule

Follow along a typical log home construction sequence of events.


100_7770

The entire construction process for a modest log home (built by a pro) ranges from four to six months, but it can run a year or more for large or complex designs. Factors that affect construction time include seasons, weather, availability of labor/subcontractors and builder expertise. Builders’ processes may vary, but use this order of events as a guide to benchmark your log home’s progress.

1. Clearing & excavating

  • Cut or grade entrance road or driveway
  • Install culverts as needed
  • Clear building site and material storage area
  • Remove trees as needed
  • Remove topsoil and store for reuse
  • Excavate basement, haul or store soil
  • Install septic tank and drain field

2. Pouring footings

  • Stake foundation corners (surveyor may do this as part of plot plan)
  • Install batter boards and layout lines
  • Locate, stake and dig footings and pier pads
  • Arrange footing inspection
  • Pour concrete for footings


100_7229

3. Installing foundation

  • Lay out foundation on footings
  • Install concrete forms for poured wall
  • Set concrete block for foundation
  • Install permanent wood foundation
  • Install waterproofing, parging or insulation board
  • Install drain tile around footings

4. Termite inspection

  • Treat soil around foundation (if necessary)

For the rest of this article, visit loghome.com!

Views: 44

Comment

You need to be a member of The Log Home Neighborhood to add comments!

Join The Log Home Neighborhood

© 2017   Created by Neighborhood Host.   Powered by

Guide to Log Homes | Advertise | Badges  |  Report an Issue  |  Terms of Service